- • Manson removed the platform with the derrick barge E.P. PAUP
• Platform weight: Deck 397 tons | Jacket 610 tons
• Water depth: 71 ft.
• Project site located 30 miles offshore
AWARDS
-
PROJECT PURPOSE
The purpose of this project was to remove a six pile oil platform in the Gulf of Mexico. The platform piles were severed, then the entire structure was lifted and placed on a barge for disposal.