FY17 MsCIP Barrier Island Restoration Cat Island Beach and Dune Fill
Cat Island, MS
PROJECT FEATURES
- • Beach restoration
• Cutter suction dredging
• Dredging approximately 2.1 million cubic yards of material
• Approximately 40 acres of beach added
AWARDS
-
PROJECT PURPOSE
The purpose of this project was to restore the eastern shoreline of Cat Island to its condition pre-Hurricane Katrina. Cat Island serves as a barrier island that protects the Mississippi’s coastal cities from damaging wave action. This project was the maiden voyage for Manson’s 30-inch cutter suction dredge, ROBERT M WHITE.