Replace U.S. Navy Berthing Piers 10 and 11

Owner: NAVFAC, Southwest
Contract Amount: $42,345,000
Location: San Diego, CA
Project Duration: 07/2000-06/2003

The purpose of this design-build project was to demolish the existing Piers 10 & 11 and construct a single replacement berthing, logistics and maintenance pier. The work included dredging and removal of approximately 536,000 cubic yards of sediment, removal of unexploded ordnance, and the construction of a new pier with a concrete deck and fender system complete with power intensive utilities to accommodate Deep Draft Power Intensive ships. The new pier is 120' wide by 1,500' long and is pile-supported on 24" octagonal concrete piling.

Manson substantially completed this project eight months ahead of schedule and received an “Outstanding” performance evaluation.